Bidding Announcement for the Construction of Road Projects on the North Extension (Phase II) of Health Avenue in Liuyang Economic Development Zone

The bidding project for the road construction of the north extension line (Phase II) of Health Avenue in Liuyang Economic Development Zone of Jingyang District was carried out by Changsha National Biological Industry Base Management Committee (Longevity [2014] No.39), Changsha National Biological Industry Base Management Committee Economic and Trade Development Bureau (Longsheng The project was approved for construction after [2014] No. 29, and the source of construction funds was self-raised. The bidder is Liuyang Economic Development Zone Investment Development Co., Ltd. (hereinafter referred to as "the tenderer"). The project has already met the conditions for tendering. The construction of the project is now open tendered nationwide.

2. Project overview and scope of tender
2.1 Project Name: Road Construction of North Extension Line (Phase II) of Health Avenue in Liuyang Economic Development Zone
2.2 Construction Site: Liuyang Economic and Technological Development Zone
2.3 Scale of the project: Health Avenue North Extension (Phase II) road project. The project line will start from Xiangtan Road in the south, and will be connected with Kaiyuan Road in Yijia Village and Dajiao Village, Dingxi Village and Lijiachong. The total length is about 3.8km. A total of about 6 flat curves are set across the line, and the minimum flat curve radius is 600m. With a design speed of 60km/h and a road width of 42m, the project will be constructed as K1+530.5-K5+297. Mainly include road engineering, culvert engineering, drainage engineering, pipeline integrated engineering (excluding gas main line pipe), afforestation project, lighting project, and traffic engineering (see specific quantities and construction drawings for details).
2.4 Quality requirements: Qualified engineering, project quality requirements are in line with the relevant national, industry, and regional construction specifications and acceptance criteria.
2.5 Duration: 480 calendar days.
2.6 Warranty Requirements: Decree No. 279 of the State Council in 2000.
2.7 Total planned investment: about RMB 116 million.
2.8 Bidding scope: The contents of the construction drawings shall prevail.
3, bidder qualification requirements
3.1 Having an independent legal personality and obtaining a business license in accordance with the law, the business license is in the period of validity. Foreign enterprises in Hunan Province must go through the basic registration of foreign enterprises in Hunan according to the requirements of Xiangjian Jianjian [2015] No. 190 (refer to “Hunan Housing and Urban and Rural Areas”. "Construction network" query prevails) or has entered the construction registration certificate (within the validity period).
3.2 The bidder must have the first class qualification of the municipal public construction contract issued by the administrative department of the industry and inquire through the two-dimensional code (according to the Xiangjian supervision [2016]111 document stipulates that the old construction enterprise qualification certificate is invalid), the safety production permit The permit is valid for a period of time and has the appropriate construction capabilities in terms of personnel, equipment, and funds.
3.3 The number of key personnel in the project department shall not be lower than the minimum standard for the provision of the document No. 57 of Xiangjian Jianjian [2015], ie at least 1 person in charge of the project, 1 person in charge of technology, 3 construction workers, 3 safety personnel, Quality staff 2 people.
3.4 The person in charge of the project must be qualified as a Grade-II registered construction engineer of a municipal public engineering professional, have an effective production-assessment qualification certificate issued by the responsible person in charge of the relevant industry administrative department, and there is no construction in progress. The person in charge of the proposed technology shall have a professional title of intermediate or above in municipal engineering or road and bridge engineering and related professional; the construction worker, quality officer, and safety officer shall have the post qualification certificate issued by the provincial or above industry administrative authority; the safety officer shall also With the provincial and above industry administrative departments issued by the safety assessment certificate C certificate.
3.5 The Commonwealth does not accept bids for this project.
3.6 Status of Projects under Construction in Key Projects of the Construction Project Department: Personnel under construction in key positions in enterprises in the province and personnel in key positions in enterprises outside the province are inspected in Hunan Province in accordance with the supervision and information platform for construction projects in Hunan Province; The company shall provide the official website of the key personnel of the construction project department without construction in progress and search results.
4, bid evaluation methods
In the evaluation phase of this project, the comprehensive assessment method I in the document No. 282 of Xiang Jianjian [2013] was adopted. The qualification review method of this project is the qualification review after the bid opening.
6. Obtaining and clarification of bid documents
6.1 From December 14th, 2016 to January 6th, 2017 at 9:00 (Beijing time, the same below)

AC Contactor

AC Contactor switch mainly used for making or breaking circuit at a long distance, suitable for controlling starting\stopping\reversing of AC motor. AC Contactor of korlen conforms to the requirement of IEC60947-4-1& GB14048.4 standards.

Except AC Contactor, there are many different types of low voltage electric appliances, such as Thermal Relay,Manual Motor Startor ,led light, Circuit Breaker, etc.

AC Contactor,Magnetic Contactor,Wafer Style Valve

Wenzhou Korlen Electric Appliances Co., Ltd. , https://www.zjthermalrelay.com